Builder's Blog Update - Week 18

By Murray Kneale, Jennian Homes

Builder's blog week 18 Thumbnail

Good progress has been made on the interior of the ASB home this week with the painters completing the ceilings and first coats on the internal walls.
 
The plan is to start applying top coats to the walls over the weekend and with the trim work (skirtings and architraves) being completed early next week.
 
The kitchen is scheduled to be installed late next week so the home is now starting to come together.
 
Contrary to the outside looking like a bomb site the landscaping has in fact started.
 
The retaining and fencing has been constructed starting from the back of the garage in the service court and this area is now ready for the firth pavers to be laid.
 
The footings and reinforcing have been completed for the terrace and the block layers will start next week to lay the terrace blocks and the blade walls to the entry area.
 
One more week and the outside should start to take shape and the completion getting closer.


Categories: News , Top 5 Articles


Disclaimer
Articles provided are for information purposes only. It is not an offer to enter into any ASB Bank Limited (ASB) products or services. Accordingly, you should not take any action in reliance of this article without considering your particular circumstances and taking appropriate professional advice. No right of action shall arise against ASB, its related companies or any of their respective directors, officers or employees either directly or indirectly as a result of the information contained in this article in particular, ASB is not responsible for any mistakes, omissions or errors in the article or matters arising due to changes to the law, products or services over time.